Inicio / Nuestros Proyectos / Obtain the update of the environmental c...
2020Obtain the update of the environmental certification and of the Environmental Adequacy and Management Program of the final disposal infrastructure “Portillo Grande Landfill”, in order to expand the operations of the infrastructure for the final disposal of municipal and non-municipal waste (industrial waste).
Cliente
INNOVA AMBIENTAL S.A
Fecha de Inicio
October of 2020
Fecha de Fin
May of 2021
Sinopsis
The objective of this service is to obtain approval of the Environmental Adequacy and Management Program (hereinafter PAMA) of the “Infrastructure for Final Disposal of Non-Hazardous Waste of the Municipal and Non-Municipal Management Scope: Portillo Grande Landfill”, based on D.S N° 010-2020-MINAM, in order to adequately manage the negative environmental impacts generated by the current operational activities and prevent those that will be generated by the enabling and/or construction activities and the continuity of the operation and closure activities, until the useful life.
The following compliance goals are established to bring the negative environmental impacts to acceptable levels:
– Maintain within the environmental quality standards for air, the levels of particulate matter and combustion gas generation, due to activities associated with the disposal of non-hazardous waste, transit through internal access roads and operation of equipment, machinery and internal combustion vehicles.
– Maintain noise levels generated by the operation of equipment, machinery and vehicles within the national environmental noise quality standard.
– Reduce any potential impact on flora and fauna.
– Improve the infrastructure related to the gas and leachate control system.
– Adapt the infrastructure for final disposal of non-hazardous waste to current regulatory requirements.
La Solución AMBIDES
Obtain approval of the Environmental Adequacy and Management Program (hereinafter PAMA) of the “Infrastructure for Final Disposal of Non-Hazardous Waste of the Municipal and Non-Municipal Management Scope: Portillo Grande Landfill”, based on D.S N° 010-2020-MINAM, in order to adequately manage the negative environmental impacts generated by current operational activities and prevent those that will be generated by the enabling and/or construction activities and the continuity of operation and closure activities, until the useful life.